Calavo County Park

Over budgeted construction bids are putting the future of Calavo Park in Jeopardy. If Spring Valley residents do not raise their concern and ask the county to find money in the budget for this park RIGHT NOW, then this park could get postponed for another couple of years or more. 

Is a Community park that will benefit so many children for decades worth two minutes of your time today? 

Estimated Construction Start: August 2024

Estimated Time To Completion: 12 - 16 Months

Latest Update: 2024-07-18

Sept 12, 2024: Scheduled Ground Breaking Ceremony 

Aug 2024: Expected Construction Start

Nov 2022:  BoS Approves Authority to Bid

Jan 2023: Currently in Final Plan Check

July 2023 :: Permitting & Review came back with Comments

Aug 2023 :: Comments are being reviewed and revisions made (No major design changes only technical construction clarification)

Sept 2023 :: Anticipated to go to Bid

Dec 23 - Jan 24 :: Estimated Construction Start

Completion :: Estimated 12 - 16 Months

Calavo Park Concept