Calavo County Park
Calavo County Park
Estimated Construction Start: August 2024
Estimated Time To Completion: 12 - 16 Months
Calavo Park Concept
Calavo Park Concept
Latest Update: 2024-07-18
Sept 12, 2024: Scheduled Ground Breaking Ceremony
Aug 2024: Expected Construction Start
Nov 2022: BoS Approves Authority to Bid
Jan 2023: Currently in Final Plan Check
July 2023 :: Permitting & Review came back with Comments
Aug 2023 :: Comments are being reviewed and revisions made (No major design changes only technical construction clarification)
Sept 2023 :: Anticipated to go to Bid
Dec 23 - Jan 24 :: Estimated Construction Start
Completion :: Estimated 12 - 16 Months